The grant will cover 71% of
the cost of three projects at Pine Hill School.and it leverages an additional $7700 in utility
incentives so that the Town share of the total estimated cost of $109,731 is
reduced to $23,931. The three projects are: Library and Gym air handler
upgrades (estimated cost: $42,775); classroom unit ventilator upgrades
(estimated cost: $36,533), and soffit insulation and air sealing (estimated
cost:$30,423).
Like the lighting and other
improvements made with the initial grant of $137,450, the improvements funded
will result in additional savings due to reduced energy consumption while
reducing Sherborn's greenhouse gas emissions. Since its designation as a Green
Community, Sherborn has reduced its energy consumption by about 15%.